• Trinity Walk Shopping Centre – Wakefield
  • Multi Storey Car Park Refurbishment

Rio were appointed by Savills to undertake the removal and replacement of the existing Mastic Asphalt waterproofing to the shoppers car park. The works covering 7,000 m²,consisted of removal of the existing Mastic Asphalt covering, replacement of central expansion joints and replacement waterproofing with a IKO Permapark Mastic Asphalt system.

To ensure footfall to the shops was unaffected during the refurbishment, only a limited number of spaces could be closed at a time therefore work had to be carried out in 5 phases over fourteen weeks. To do so we needed to increase the project time by two weeks to allow for the moving of fencing and barriers to each phase.